Quatation Creation
Enter Project Details
Add Additional FieldsQuotation ID : #SCQ001
Client : Chandhu
Location : Bangalore, Karnataka
Construction Estimate
Quotation ID : #SCQ001
Client : Chandhu
Location : Bangalore, Karnataka
| Sl No | Category | Unit | Length | Width | Unit Count | Unit Cost | Tax | Total Cost |
|---|---|---|---|---|---|---|---|---|
| 01 | Slab Area Ground Floor | sqft | 50 | 40 | 2000 | 1,800.00 | 36,00,000.00 | |
| 02 | Slab Area First Floor | sqft | 50 | 40 | 2000 | 1,800.00 | 36,00,000.00 | |
| 03 | Slab Area Second Floor | sqft | 50 | 40 | 2000 | 1,800.00 | 36,00,000.00 | |
| 04 | Slab Area Third Floor | sqft | 50 | 40 | 2000 | 1,800.00 | 36,00,000.00 | |
| 05 | Slab Area Fourth Floor | sqft | 50 | 40 | 2000 | 1,800.00 | 36,00,000.00 | |
| 06 | Slab Area Fifth Floor | sqft | 20 | 20 | 520 | 1,800.00 | 9,36,000.00 |
Additional work
Add Additional Work| Sl No | Category | Unit | Length | Width | Unit Count | Unit Cost | Tax | Total Cost |
|---|---|---|---|---|---|---|---|---|
| 07 | Demolition & Dismantling | sqft | 10 | 20 | 200 | 800.00 | 1,60,000.00 | |
| 08 | Waterproofing & Insulation | sqft | 10 | 20 | 200 | 800.00 | 1,60,000.00 |
Interior work
Add Interior Work| Sl No | Category | Unit | Length | Width | Unit Count | Unit Cost | Tax | Total Cost |
|---|---|---|---|---|---|---|---|---|
| 09 | False Ceiling & Lighting Design | sqft | 10 | 20 | 200 | 800.00 | 1,60,000.00 | |
| 10 | Modular Furniture Design | sqft | 10 | 20 | 200 | 800.00 | 1,60,000.00 |
Total Amount
| Sl No | Category | Unit Count | Unit Cost | Tax | Total Cost | Discount - Unit Cost | Total Cost - After Discount |
|---|---|---|---|---|---|---|---|
| 11 | Construction Estimate | 10520.00 | 1800.00 | 1,89,36,000.00 | 50 | 1,84,10,000.00 | |
| 12 | Additional work | 400.00 | 800.00 | 3,20,000.00 | 50 | 3,00,000.00 | |
| 13 | Interior work | 400.00 | 800.00 | 3,20,000.00 | 50 | 3,00,000.00 | |
| 14 | Project Cost After Discount | 11,320.00 | 1,95,76,000.00 | 1,90,10,000.00 |
Payment Schedule
Quotation ID : #SCQ001
Client : Chandhu
Location : Bangalore, Karnataka
| Sl No | Schedule | % Of Final Quote | Payment Date | Payment Amount |
|---|---|---|---|---|
| 01 | Mobilisation, Designs & Drawings | 2% | 1 May 2025 | ₹ 1,94,424.00 |
| 02 | Foundation Works | 12% | 1 Jun 2025 | ₹ 11,66,544.00 |
| 03 | Structural work Floor Ground | 9% | 1 July 2025 | ₹ 8,74,908.00 |
| 04 | Structural work Floor 1 | 9% | 1 August 2025 | ₹ 8,74,908.00 |
| 05 | Structural work Floor 2 | 9% | 1 Sep 2025 | ₹ 8,74,908.00 |
| 06 | Structural work Floor 3 | 9% | 1 Oct 2025 | ₹ 8,74,908.00 |
| 07 | Pre plastering | 5% | 1 Nov 2025 | ₹ 4,86,060.00 |
| 08 | Plastering | 10% | 1 Dec 2025 | ₹ 9,72,120.00 |
| 09 | Finishing stage 1 | 10% | 1 Jan 2026 | ₹ 9,72,120.00 |
| 10 | Finishing stage 2 | 10% | 1 Feb 2026 | ₹ 9,72,120.00 |
| 11 | Finishing stage 3 | 10% | 1 March 2026 | ₹ 9,72,120.00 |
| 12 | Cleaning and handover | 4% | 1 April 2026 | ₹ 3,88,848.00 |
| 13 | Handover | 1% | 1 May 2026 | ₹ 97,212.00 |
| Total | 100% | 1 Jun 2026 | ₹ 97,21,200.00 |
Work Schedule
Quotation ID : #SCQ001
Client : Chandhu
Location : Bangalore, Karnataka
| Schedule Name | Stage Name | No Of Days | Start Date | End Date | |
|---|---|---|---|---|---|
| Mobilisation, Designs & Drawings | 1 | Mobilisation, Designs & Drawings | 30 | 1 May 2025 | 31 May 2025 |
| Foundation Works | |||||
| 2 | Excavation and PCC | 15 | 1 Jun 2025 | 16 Jun 2025 | |
| 3 | Footing | 15 | 17 Jun 2025 | 2 Jul 2025 | |
| 4 | Backfilling and Plinth Beam | 15 | 3 Jul 2025 | 18 Jul 2025 | |
| 5 | Water curing | 15 | 19 Jul 2025 | 3 Aug 2025 | |
| Structural work Floor Ground | |||||
| 6 | Column rising, blockwork up to lintel level for Floor Ground |
22 | 4 Aug 2025 | 26 Aug 2025 | |
| 7 | Casting the lintels, staircase, blockwork up to the slab level for Floor Ground |
15 | 17 Jun 2025 | 2 Jul 2025 | |
| 8 | RCC slab for roof level. for Floor Ground | 7 | 4 Sep 2025 | 11 Sep 2025 | |
| 9 | Water curing Floor Ground | 14 | 12 Sep 2025 | 26 Sep 2025 | |
| Structural work Floor 1 | |||||
| 10 | Column rising, blockwork up to lintel level for Floor 1 |
22 | 27 Sep 2025 | 19 Oct 2025 | |
| 11 | Casting the lintels, staircase, blockwork up to the slab level for Floor 1 |
7 | 20 Oct 2025 | 27 Oct 2025 | |
| 12 | RCC slab for roof level. for Floor 1 |
7 | 28 Oct 2025 | 4 Nov 2025 | |
| 13 | Water curing Floor 1 | 14 | 5 Nov 2025 | 19 Nov 2025 | |
| Structural work Floor 2 | |||||
| 14 | Column rising, blockwork up to lintel level for Floor 2 |
22 | 20 Nov 2025 | 12 Dec 2025 | |
| 15 | Casting the lintels, staircase, blockwork up to the slab level for Floor 2 |
7 | 13 Dec 2025 | 20 Dec 2025 | |
| 16 | RCC slab for roof level. for Floor 2 |
7 | 21 Dec 2025 | 28 Dec 2025 | |
| 17 | Water curing Floor 2 | 14 | 29 Dec 2025 | 12 Jan 2026 | |
| Structural work Floor 3 | |||||
| 18 | Column rising, blockwork up to lintel level for Floor 3 |
22 | 13 Jan 2026 | 4 Feb 2026 | |
| 19 | Casting the lintels, staircase, blockwork up to the slab level for Floor 3 |
7 | 5 Feb 2026 | 12 Feb 2026 | |
| 20 | RCC slab for roof level. for Floor 3 |
7 | 13 Feb 2026 | 20 Feb 2026 | |
| 21 | Water curing Floor 3 | 14 | 21 Feb 2026 | 7 Mar 2026 | |
| Pre plastering Floor Ground |
|||||
| 22 | Doors & windows | 2 | 8 Mar 2026 | 10 Mar 2026 | |
| 23 | Plumbing line setting | 4 | 11 Mar 2026 | 15 Mar 2026 | |
| 24 | Electric line Setting | 4 | 16 Mar 2026 | 20 Mar 2026 | |
| Pre plastering Floor 1 | |||||
| 25 | Doors & Windows | 2 | 21 Mar 2026 | 23 Mar 2026 | |
| 26 | Plumbing line setting | 4 | 24 Mar 2026 | 28 Mar 2026 | |
| 27 | Electric line Setting | 4 | 29 Mar 2026 | 2 Apr 2026 | |
| Pre plastering Floor 3 | |||||
| 31 | Doors & windows | 2 | 16 Apr 2026 | 18 Apr 2026 | |
| 32 | Plumbing line setting | 4 | 19 Apr 2026 | 23 Apr 2026 | |
| 33 | Electric line Setting | 4 | 24 Apr 2026 | 28 Apr 2026 | |
| Plastering floor ground | |||||
| 34 | External Plastering Floor Ground | 7 | 29 Apr 2026 | 6 May 2026 | |
| 35 | Internal Plastering for Floor ground | 7 | 7 May 2026 | 14 May 2026 | |
| Plastering floor 1 | |||||
| 36 | External Plastering Floor 1 | 7 | 15 May 2026 | 22 May 2026 | |
| 37 | Internal Plastering for Floor 1 | 7 | 23 May 2026 | 30 May 2026 | |
| Plastering floor 2 | |||||
| 38 | External Plastering Floor 2 | 7 | 31 May 2026 | 7 Jun 2026 | |
| 39 | Internal Plastering for Floor 2 | 7 | 8 Jun 2026 | 15 Jun 2026 | |
| Plastering floor 3 | |||||
| 40 | External Plastering Floor 2 | 7 | 16 Jun 2026 | 23 Jun 2026 | |
| 41 | Internal Plastering for Floor 2 | 7 | 24 Jun 2026 | 1 Jul 2026 | |
| Finishing stage 1 - Floor ground | |||||
| 42 | Internal & External Painting - Putty works | 4 | 2 Jul 2026 | 6 Jul 2026 | |
| 43 | Flooring for GF | 4 | 7 Jul 2026 | 11 Jul 2026 | |
| 44 | Wall cladding for GF | 4 | 12 Jul 2026 | 16 Jul 2026 | |
| Finishing stage 1- floor 1 | |||||
| 45 | Internal & External Painting - Putty works | 4 | 17 Jul 2026 | 21 Jul 2026 | |
| 46 | Flooring for GF | 4 | 22 Jul 2026 | 26 Jul 2026 | |
| 47 | Wall cladding for GF | 4 | 27 Jul 2026 | 31 Jul 2026 | |
| Finishing stage 1 - floor 2 | |||||
| 48 | Internal & External Painting - Putty works | 4 | 1 Aug 2026 | 5 Aug 2026 | |
| 49 | Flooring for GF | 4 | 6 Aug 2026 | 10 Aug 2026 | |
| 50 | Wall cladding for GF | 4 | 11 Aug 2026 | 15 Aug 2026 | |
| Finishing stage 1- floor 3 | |||||
| 51 | Internal & External Painting - Putty works | 4 | 16 Aug 2026 | 20 Aug 2026 | |
| 52 | Flooring for GF | 4 | 21 Aug 2026 | 25 Aug 2026 | |
| 53 | Wall cladding for GF | 4 | 26 Aug 2026 | 30 Aug 2026 | |
| Finishing stage 2- floor ground | |||||
| 54 | Supply of Doors, Windows, | 4 | 31 Aug 2026 | 4 Sep 2026 | |
| 55 | Fabrication works | 4 | 5 Sep 2026 | 9 Sep 2026 | |
| 56 | Electrical fixtures, | 4 | 10 Sep 2026 | 14 Sep 2026 | |
| Finishing stage 2 - floor 1 | |||||
| 57 | Supply of Doors, Windows | 4 | 15 Sep 2026 | 19 Sep 2026 | |
| 58 | Fabrication works | 4 | 20 Sep 2026 | 24 Sep 2026 | |
| 59 | 9 Electrical fixtures | 4 | 25 Sep 2026 | 29 Sep 2026 | |
| Finishing stage 2- Floor 2 | |||||
| 60 | Supply of Doors, Windows | 4 | 30 Sep 2026 | 4 Oct 2026 | |
| 61 | Fabrication works | 4 | 5 Oct 2026 | 9 Oct 2026 | |
| 62 | Electrical Fixtures | 4 | 10 Oct 2026 | 14 Oct 2026 | |
| Finishing stage 2- floor 3 | |||||
| 63 | Supply of Doors, Windows | 4 | 15 Oct 2026 | 19 Oct 2026 | |
| 64 | Fabrication works | 4 | 20 Oct 2026 | 24 Oct 2026 | |
| 65 | Electrical Fixtures | 4 | 25 Oct 2026 | 29 Oct 2026 | |
| Finishing stage 3- Floor ground | |||||
| 66 | Internal & External Painting - 1st coat | 4 | 30 Oct 2026 | 3 Nov 2026 | |
| 67 | Internal & External Painting - Final coat | 4 | 4 Nov 2026 | 8 Nov 2026 | |
| 68 | Plumbing fittings | 4 | 9 Nov 2026 | 13 Nov 2026 | |
| Finishing stage 3- floor 1 | |||||
| 69 | Internal & External Painting - 1st coat | 4 | 14 Nov 2026 | 18 Nov 2026 | |
| 70 | Internal & External Painting - Final coat | 4 | 19 Nov 2026 | 23 Nov 2026 | |
| 71 | Plumbing fittings | 4 | 24 Nov 2026 | 28 Nov 2026 | |
| Finishing stage 3 - floor 2 | |||||
| 72 | Internal & External Painting - 1st coat | 4 | 29 Nov 2026 | 3 Dec 2026 | |
| 73 | Internal & External Painting - Final coat | 4 | 4 Dec 2026 | 8 Dec 2026 | |
| 74 | Plumbing fittings | 4 | 9 Dec 2026 | 13 Dec 2026 | |
| Finishing stage 3- floor 3 | |||||
| 75 | Internal & External Painting - 1st coat | 4 | 14 Dec 2026 | 18 Dec 2026 | |
| 76 | Internal & External Painting - Final coat | 4 | 19 Dec 2026 | 23 Dec 2026 | |
| 77 | Plumbing fittings | 4 | 24 Dec 2026 | 28 Dec 2026 | |
| Cleaning | 78 | Final Miscellaneous works and cleaning | 4 | 29 Dec 2026 | 13 Jan 2027 |
| Handover | 79 | Keys Handing over with letter | 1 | 14 Jan 2027 | 15 Jan 2027 |