837 655 36 170 324
Materials Estimate
Work Sl Material Unit GF FF SF Comp Mould Total Qty Rate Total Cost
Structure 1 6" Bricks Number 1046.25 818.75 45 765 405 3080 40 123200
2 4" Bricks Number 418.5 327.5 18 0 0 764 30 22920
3 Steel Kg 2845.8 2227 122.4 578 1101.6 6874.8 60 412488
Total Material Cost 1926936.15
Labour Estimate
Work Sl Name Unit GF FF SF Comp Mould Total Qty Rate Total Cost
Structure / Civil 1 Mason Chadar / Sqft 837 655 36 0 324 1852 250 463000
2 Barbender Chadar / Sqft 837 655 36 0 324 1852 35 64820
3 Shuttering Chadar / Sqft 2092.5 1310 72 0 648 4122.5 35 144287.5
Total Labour Cost 962442.8875
Additional Work Estimate
Work Sl Description Unit Ground Floor First Floor Second Floor Compound Mould Total Qty Rate Total Cost
Additional 1 Extra Mason Work Sqft 0 0 0 170 0 170 250 42500
2 Extra Plumbing Work Sqft 0 0 0 0 100 100 200 20000
3 Extra Electrical Work Sqft 0 0 0 0 50 50 300 15000
Total Additional Work Cost 77500
Total Estimation Cost
Material Cost 1926936.15
Labour Cost 962442.8875
Additional Work Cost 77500
Total Project Cost 2889379.04