Project Details
| Enter Details | Ground Floor | First Floor | Second Floor | Compound | Mould Extension | |||
|---|---|---|---|---|---|---|---|---|
| 837 | 655 | 36 | 170 | 324 | ||||
Materials Estimate
| Work | Sl | Material | Unit | GF | FF | SF | Comp | Mould | Total Qty | Rate | Total Cost |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Structure | 1 | 6" Bricks | Number | 1046.25 | 818.75 | 45 | 765 | 405 | 3080 | 40 | 123200 |
| 2 | 4" Bricks | Number | 418.5 | 327.5 | 18 | 0 | 0 | 764 | 30 | 22920 | |
| 3 | Steel | Kg | 2845.8 | 2227 | 122.4 | 578 | 1101.6 | 6874.8 | 60 | 412488 | |
| Total Material Cost | 1926936.15 | ||||||||||
Labour Estimate
| Work | Sl | Name | Unit | GF | FF | SF | Comp | Mould | Total Qty | Rate | Total Cost |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Structure / Civil | 1 | Mason | Chadar / Sqft | 837 | 655 | 36 | 0 | 324 | 1852 | 250 | 463000 |
| 2 | Barbender | Chadar / Sqft | 837 | 655 | 36 | 0 | 324 | 1852 | 35 | 64820 | |
| 3 | Shuttering | Chadar / Sqft | 2092.5 | 1310 | 72 | 0 | 648 | 4122.5 | 35 | 144287.5 | |
| Total Labour Cost | 962442.8875 | ||||||||||
Additional Work Estimate
| Work | Sl | Description | Unit | Ground Floor | First Floor | Second Floor | Compound | Mould | Total Qty | Rate | Total Cost |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Additional | 1 | Extra Mason Work | Sqft | 0 | 0 | 0 | 170 | 0 | 170 | 250 | 42500 |
| 2 | Extra Plumbing Work | Sqft | 0 | 0 | 0 | 0 | 100 | 100 | 200 | 20000 | |
| 3 | Extra Electrical Work | Sqft | 0 | 0 | 0 | 0 | 50 | 50 | 300 | 15000 | |
| Total Additional Work Cost | 77500 | ||||||||||
Total Estimation Cost
| Material Cost | 1926936.15 | ||||||||||
| Labour Cost | 962442.8875 | ||||||||||
| Additional Work Cost | 77500 | ||||||||||
| Total Project Cost | 2889379.04 | ||||||||||