Add Requirements

Construction Estimate

Sl No Category Unit Length Width Unit Count Unit Cost Tax Total Cost
01 Slab Area Ground Floor sqft 50 40 2000 1,800.00 36,00,000.00
02 Slab Area First Floor sqft 50 40 2000 1,800.00 36,00,000.00
03 Slab Area Second Floor sqft 50 40 2000 1,800.00 36,00,000.00
04 Slab Area Third Floor sqft 50 40 2000 1,800.00 36,00,000.00
05 Slab Area Fourth Floor sqft 50 40 2000 1,800.00 36,00,000.00
06 Slab Area Fifth Floor sqft 20 20 520 1,800.00 9,36,000.00

Additional work

Add Additional Work
Sl No Category Unit Length Width Unit Count Unit Cost Tax Total Cost
07 Demolition & Dismantling sqft 10 20 200 800.00 1,60,000.00
08 Waterproofing & Insulation sqft 10 20 200 800.00 1,60,000.00

Inerior work

Add Interior Work
Sl No Category Unit Length Width Unit Count Unit Cost Tax Total Cost
09 False Ceiling & Lighting Design sqft 10 20 200 800.00 1,60,000.00
10 Modular Furniture Design sqft 10 20 200 800.00 1,60,000.00

Total Amount

Sl No Category Unit Length Width Unit Count Unit Cost Tax Total Cost
11 Total Built Up Area 10520 1800.00 1,89,36,000.00
12 Discount 10520 50.00 5,26,000.00
13 Project Cost After Discount 1750.00 1,84,10,000.00
Sl No Schedule % Of Final Quote Payment Amount
01 Mobilisation, Designs & Drawings 2% ₹ 1,94,424.00
02 Foundation Works 12% ₹ 11,66,544.00
03 Structural work Floor Ground 9% ₹ 8,74,908.00
04 Structural work Floor 1 9% ₹ 8,74,908.00
05 Structural work Floor 2 9% ₹ 8,74,908.00
06 Structural work Floor 3 9% ₹ 8,74,908.00
07 Pre plastering 5% ₹ 4,86,060.00
08 Plastering 10% ₹ 9,72,120.00
09 Finishing stage 1 10% ₹ 9,72,120.00
10 Finishing stage 2 10% ₹ 9,72,120.00
11 Finishing stage 3 10% ₹ 9,72,120.00
12 Cleaning and handover 4% ₹ 3,88,848.00
13 Handover 1% ₹ 97,212.00
Total 100% ₹ 97,21,200.00
Schedule Name Stage Name No Of Days Start Date End Date
Mobilisation, Designs & Drawings 1 Mobilisation, Designs & Drawings 30 1 May 2025 31 May 2025
Foundation Works
2 Excavation and PCC 15 1 Jun 2025 16 Jun 2025
3 Footing 15 17 Jun 2025 2 Jul 2025
4 Backfilling and Plinth Beam 15 3 Jul 2025 18 Jul 2025
5 Water curing 15 19 Jul 2025 3 Aug 2025
Structural work Floor Ground
6 Column rising, blockwork up to
lintel level for Floor Ground
22 4 Aug 2025 26 Aug 2025
7 Casting the lintels, staircase,
blockwork up to the slab level for Floor Ground
15 17 Jun 2025 2 Jul 2025
8 RCC slab for roof level. for Floor Ground 7 4 Sep 2025 11 Sep 2025
9 Water curing Floor Ground 14 12 Sep 2025 26 Sep 2025
Structural work Floor 1
10 Column rising, blockwork
up to lintel level for Floor 1
22 27 Sep 2025 19 Oct 2025
11 Casting the lintels, staircase,
blockwork up to the slab level
for Floor 1
7 20 Oct 2025 27 Oct 2025
12 RCC slab for roof level.
for Floor 1
7 28 Oct 2025 4 Nov 2025
13 Water curing Floor 1 14 5 Nov 2025 19 Nov 2025
Structural work Floor 2
14 Column rising, blockwork up to
lintel level for Floor 2
22 20 Nov 2025 12 Dec 2025
15 Casting the lintels, staircase,
blockwork up to the slab level
for Floor 2
7 13 Dec 2025 20 Dec 2025
16 RCC slab for roof level. for
Floor 2
7 21 Dec 2025 28 Dec 2025
17 Water curing Floor 2 14 29 Dec 2025 12 Jan 2026
Structural work Floor 3
18 Column rising, blockwork up to
lintel level for Floor 3
22 13 Jan 2026 4 Feb 2026
19 Casting the lintels, staircase,
blockwork up to the slab level
for Floor 3
7 5 Feb 2026 12 Feb 2026
20 RCC slab for roof level. for
Floor 3
7 13 Feb 2026 20 Feb 2026
21 Water curing Floor 3 14 21 Feb 2026 7 Mar 2026
Pre plastering Floor
Ground
22 Doors & windows 2 8 Mar 2026 10 Mar 2026
23 Plumbing line setting 4 11 Mar 2026 15 Mar 2026
24 Electric line Setting 4 16 Mar 2026 20 Mar 2026
Pre plastering Floor 1
25 Doors & Windows 2 21 Mar 2026 23 Mar 2026
26 Plumbing line setting 4 24 Mar 2026 28 Mar 2026
27 Electric line Setting 4 29 Mar 2026 2 Apr 2026
Pre plastering Floor 3
31 Doors & windows 2 16 Apr 2026 18 Apr 2026
32 Plumbing line setting 4 19 Apr 2026 23 Apr 2026
33 Electric line Setting 4 24 Apr 2026 28 Apr 2026
Plastering floor ground
34 External Plastering Floor Ground 7 29 Apr 2026 6 May 2026
35 Internal Plastering for Floor ground 7 7 May 2026 14 May 2026
Plastering floor 1
36 External Plastering Floor 1 7 15 May 2026 22 May 2026
37 Internal Plastering for Floor 1 7 23 May 2026 30 May 2026
Plastering floor 2
38 External Plastering Floor 2 7 31 May 2026 7 Jun 2026
39 Internal Plastering for Floor 2 7 8 Jun 2026 15 Jun 2026
Plastering floor 3
40 External Plastering Floor 2 7 16 Jun 2026 23 Jun 2026
41 Internal Plastering for Floor 2 7 24 Jun 2026 1 Jul 2026
Finishing stage 1 - Floor ground
42 Internal & External Painting - Putty works 4 2 Jul 2026 6 Jul 2026
43 Flooring for GF 4 7 Jul 2026 11 Jul 2026
44 Wall cladding for GF 4 12 Jul 2026 16 Jul 2026
Finishing stage 1- floor 1
45 Internal & External Painting - Putty works 4 17 Jul 2026 21 Jul 2026
46 Flooring for GF 4 22 Jul 2026 26 Jul 2026
47 Wall cladding for GF 4 27 Jul 2026 31 Jul 2026
Finishing stage 1 - floor 2
48 Internal & External Painting - Putty works 4 1 Aug 2026 5 Aug 2026
49 Flooring for GF 4 6 Aug 2026 10 Aug 2026
50 Wall cladding for GF 4 11 Aug 2026 15 Aug 2026
Finishing stage 1- floor 3
51 Internal & External Painting - Putty works 4 16 Aug 2026 20 Aug 2026
52 Flooring for GF 4 21 Aug 2026 25 Aug 2026
53 Wall cladding for GF 4 26 Aug 2026 30 Aug 2026
Finishing stage 2- floor ground
54 Supply of Doors, Windows, 4 31 Aug 2026 4 Sep 2026
55 Fabrication works 4 5 Sep 2026 9 Sep 2026
56 Electrical fixtures, 4 10 Sep 2026 14 Sep 2026
Finishing stage 2 - floor 1
57 Supply of Doors, Windows 4 15 Sep 2026 19 Sep 2026
58 Fabrication works 4 20 Sep 2026 24 Sep 2026
59 9 Electrical fixtures 4 25 Sep 2026 29 Sep 2026
Finishing stage 2- Floor 2
60 Supply of Doors, Windows 4 30 Sep 2026 4 Oct 2026
61 Fabrication works 4 5 Oct 2026 9 Oct 2026
62 Electrical Fixtures 4 10 Oct 2026 14 Oct 2026
Finishing stage 2- floor 3
63 Supply of Doors, Windows 4 15 Oct 2026 19 Oct 2026
64 Fabrication works 4 20 Oct 2026 24 Oct 2026
65 Electrical Fixtures 4 25 Oct 2026 29 Oct 2026
Finishing stage 3- Floor ground
66 Internal & External Painting - 1st coat 4 30 Oct 2026 3 Nov 2026
67 Internal & External Painting - Final coat 4 4 Nov 2026 8 Nov 2026
68 Plumbing fittings 4 9 Nov 2026 13 Nov 2026
Finishing stage 3- floor 1
69 Internal & External Painting - 1st coat 4 14 Nov 2026 18 Nov 2026
70 Internal & External Painting - Final coat 4 19 Nov 2026 23 Nov 2026
71 Plumbing fittings 4 24 Nov 2026 28 Nov 2026
Finishing stage 3 - floor 2
72 Internal & External Painting - 1st coat 4 29 Nov 2026 3 Dec 2026
73 Internal & External Painting - Final coat 4 4 Dec 2026 8 Dec 2026
74 Plumbing fittings 4 9 Dec 2026 13 Dec 2026
Finishing stage 3- floor 3
75 Internal & External Painting - 1st coat 4 14 Dec 2026 18 Dec 2026
76 Internal & External Painting - Final coat 4 19 Dec 2026 23 Dec 2026
77 Plumbing fittings 4 24 Dec 2026 28 Dec 2026
Cleaning 78 Final Miscellaneous works and cleaning 4 29 Dec 2026 13 Jan 2027
Handover 79 Keys Handing over with letter 1 14 Jan 2027 15 Jan 2027